Twelve Whyalla projects were on the table for discussion at last night’s City of Whyalla information session.

Council CEO Chris Cowley, elected members and senior Council officers were on hand at the Whyalla Public Library to reveal details of the projects and invite discussions and questions from the public.

Mr Cowley thanked the four members of the public who attended the evening.

“These residents saw a detailed presentation on these 12 projects, asked some great questions and provided us with some valuable feedback,” Mr Cowley said.

“These sessions followed our information sharing and public consultation session held at the Westland Shopping Centre last week.

“Along with our regular communications through our website, social media, letter box drops, adverts and press releases, we will continue to hold these sorts of sessions to keep everyone in the loop and encourage feedback and community ownership of these projects.”

The projects presented last night included the new jetty, Bennett Oval redevelopment, Civic Park solar lights and CCTV, marina moorings, old airport hangar refurbishment, bike and walking paths, stormwater plans, city entrance signs, wetlands wharf, playground upgrades, beach access canopy refurbishment and Hummock Hill lighting.

“Some of the projects have been completed, some are about to start and some are still in the public consultation stage,” Mr Cowley said.

“That’s why these public information and consultation sessions are so important to find out what the community wants as we strive to make our city even better.

“They also allow us to give residents an insight into Council workings and the decision-making process.”

WHYALLA’S 12 PROJECTS

informationsession
NEW JETTY

Location: Whyalla foreshore at the site of the existing jetty

Cost: $6.5m

Start date: April 2019

Contractor: Maritime Constructions (Adelaide) using local labour, materials and contractors of about $2.5m value.

informationsession
BENNETT OVAL

Location: McDouall Stuart Avenue

Cost: Stage 1 estimated $2.8m

Estimated start date: August 2019

Contractor: TBA

informationsession
CIVIC PARK SOLAR LIGHTS AND CCTV

Location: Nicolson Avenue

Cost: $400,000 (Grant funding of $364,000)

Estimated start date: April 2019

Contractor: ATI Australia (Adelaide) and CEM (Adelaide) both using Whyalla contractors

informationsession
MARINA MOORINGS

Location: Whyalla Marina

Cost: $386,810

Estimated start date: May-June 2019

Contractor: Walcon Marine Australasia (Mandurah WA) using McMahon Services (Whyalla)

informationsession
OLD AIRPORT HANGAR REFURBISHMENT

Location: Keith St, Whyalla

Cost: $117,238

Start date: March 2019

Contractor: McMullen Builders (Whyalla)

informationsession
COMBINED BIKE AND WALKING PATH

Location: Heurich Tce and Ekblom St

Cost: $117,000

Start date: February 2019 (almost complete)

Contractor: A&G D’Orazio & Co (Whyalla)

informationsession
STORMWATER MANAGEMENT PLAN

Location: Whyalla city

Cost: TBA. Jointly funded by Stormwater Management Authority, Natural Disaster Resilience Program and Council.

Start date: Currently in public consultation stage.

Contractor: TBA

informationsession
CITY ENTRANCE SIGNS

Location: TBA on Port August and Port Lincoln entrances to Whyalla.

Cost: $100,000 ($35,000 grant from the City Entrance Upgrades fund)

Start date: Pending approval from Department of Planning, Transport and Infrastructure. Public consultation completed to select designs

Contractor: TBA

informationsession
WETLANDS WHARF

Location: Jim Pollock Whyalla Wetlands on Lincoln Hwy

Cost: $50,000

Start date: Completed

Contractor: Seaslip (NSW) using Whyalla contractor Diggers Civil

informationsession
PLAYGROUND FENCING

Location: Trevan St, Field St and Point Lowly

Cost: $31,000

Start date: Completed

Contractor: See Us Maintenance (Whyalla) A&G D’Orazio & Co (Whyalla)

informationsession
BEACH ACCESS CANOPY REFURBISHMENT

Location: Whyalla foreshore

Cost: Estimated $75,000

Start date: March 2019 (in progress)

Contractor: M.J.M Abrasive Blasting (Whyalla)

informationsession
HUMMOCK HILL LIGHTING

Location: Hummock Hill, Whyalla

Cost: $57,897

Estimate start date: April 2019

Contractor: Total Green – Green Power (Adelaide) using Whyalla contractor Dunstall Excavations.