- Latest News

The Whyalla jetty project passed another milestone this month with the completion of detailed tender drawings and manufacturing specifications.
This means we now know what sort of steel pylons, concrete planks etc are going to be needed for this exciting new structure. The tender drawings have also allowed for the production of 3D images further showing how the jetty is going to look (see pictures).
One of the specifications in the drawings shows the jetty is expected to be higher than the existing breakwater to safeguard it against future natural occurrences and changes in weather patterns. This would require construction work on the breakwater leading up to the jetty to provide a gradual ramp to make it accessible to those in wheelchairs and important vehicles such as ambulances and rescue services.
We also know what the shelter structures are going to look like after design consultants Magryn and Associates confirmed the proposed roof structures were suitable.
The new 165m jetty extends beyond the Council boundary by about 35m so Council will now submit a development application to the State Commission Assessment Panel (SCAP) for approval.
In conjunction with the SCAP approval, Council will acquire an endorsement from the State Government for the proposed development. This application process will be undertaken in conjunction with the tendering process.
Work is now progressing on the tender document for a building contractor. This document is expected to be released for submissions in early July with a four-week cut-off.
Council’s intention, as the project manager, is to have one main contractor while ensuring maximum benefit for local contractors, suppliers and workers where possible.
City of Whyalla CEO Chris Cowley said Council was progressing with the processes as quickly as possible without compromising the due diligence and responsibility Council has in providing this important community asset.
“For this project every measure of due diligence has to be met, every regulatory approval has to be satisfied and we are making sure this is a structure that meets the community needs and will last a long time,” Mr Cowley said.
“We are endeavouring to do this the most efficient way for the best possible cost and with as much local input when it comes to labour and materials.”
Work has already been completed near the site to install a new power cable capable of supporting the breakwater lights and any future power supply needs on the new jetty. Work this month to strengthen the southern breakwater was also important for the jetty and surrounding structures.